Silver Lake ADU
Website Portfolio Description
Rolen Construction is currently completing the Silver Lake ADU, a two-story accessory dwelling unit created through the conversion of an existing garage and the construction of a new residential addition. Located in the heart of Silver Lake, the project delivers a modern 2-bedroom, 2-bathroom living space featuring contemporary architectural design, energy-efficient systems, and an elevated outdoor deck.
The project demonstrates Rolen Construction’s expertise in ADU construction, complex residential additions, and high-quality finish execution within dense urban environments. By transforming an underutilized structure into a fully functional residence, the project enhances property value while contributing additional housing inventory within one of Los Angeles’ most desirable neighborhoods.
As General Contractor, Rolen Construction has coordinated all phases of construction, from demolition and structural improvements through interior finishes and final detailing, ensuring quality workmanship and efficient project delivery throughout the build.
Project Facts
- Project Name: Silver Lake ADU
- Location: 1430 3/4 Silver Lake Blvd, Los Angeles, CA 90026
- Project Type: Accessory Dwelling Unit (ADU)
- General Contractor: Rolen Construction
- Architect: Dialectic Architecture
- Construction Start: March 2025
- Estimated Completion: July 2026
- Current Status: Finishes Phase
- Bedrooms: 2
- Bathrooms: 2
- Structure: Two-Story ADU
- Scope: Garage Conversion + New Addition + Exterior Deck
- Approximate ADU Area: 1,058 SF
Construction Highlights
- Conversion of an existing detached garage into a fully code-compliant residential ADU
- Construction of a new second-story addition
- Modern exterior deck and outdoor living area
- Structural upgrades for residential occupancy
- New mechanical, electrical, and plumbing systems
- Energy-efficient construction and Title 24 compliance
- Construction within a constrained urban hillside environment
- Contemporary architectural detailing and open-concept living spaces
Project Update
Project Status: Finishes Phase
Construction began in March 2025 and has successfully progressed through demolition, structural framing, rough mechanical/electrical/plumbing installation, exterior envelope completion, and interior drywall phases.
The project is currently in the finishes stage, with interior millwork, cabinetry, flooring, painting, fixtures, and final architectural details being installed. Exterior improvements and deck finishes are also advancing toward completion.
Key Milestones Achieved
- Demolition completed
- Structural upgrades completed
- Framing completed
- Roofing completed
- Exterior envelope completed
- Mechanical, electrical, and plumbing rough-ins completed
- Insulation completed
- Drywall completed
- Interior finish installation underway
Current Activities
- Interior finishes
- Cabinetry installation
- Painting
- Flooring installation
- Fixture installation
- Exterior deck finishing
- Final detailing
Expected Completion
July 2026
Project Duration
March 2025 – July 2026